Under the NIST SP 800-171 REV.2 / CMMC 2.0 Level 2 framework, this control requires that any proposed change to systems be reviewed in advance to identify possible impacts on confidentiality, integrity, or availability. The objective is simple: before a change is made, the security impact is analyzed, and any risks identified are mitigated or the change rejected. Failing to do that can introduce vulnerabilities, break protections, or disrupt service, so the practice must be formalized and repeatable.
Technical Implementation
-
Formal change control policy and Change Control Board (CCB).
Create a concise written policy that makes security impact analysis a mandatory step for all changes to production systems. Define who sits on the CCB (at minimum: a system/network administrator, a security owner, and an operations lead) and require CCB approval before implementation. For SMBs, meet weekly or on-demand for emergency changes.
-
Standardized change request template with a Security Impact Analysis section.
Use your ticketing tool (helpdesk, Jira, ServiceNow, or even a shared form) to capture: affected assets, data sensitivity, authentication/authorization changes, third-party components, expected downtime, rollback plan, test plan, and estimated risk level. Require author, dates, and explicit security owner sign-off before scheduling.
-
Risk checklist and simple scoring criteria.
Give reviewers a short checklist to assess CIA impacts: will confidentiality be reduced, could integrity be compromised, will availability be affected? Use a three-level impact score (High/Medium/Low) and define accept/mitigate/reject thresholds so small teams can make consistent, defensible decisions quickly.
-
Require pre-deployment testing and a rollback plan.
Make testing in a staging or test environment mandatory for non-trivial changes. Capture test results and require a documented rollback procedure and a verified backup/snapshot before the change. For hardware changes (e.g., RAM upgrade) or software removals, validate on a representative system and sign off before production.
-
Implementation window, monitoring, and post-change verification.
Schedule vetted changes during agreed maintenance windows; instrument monitoring and logging to detect issues immediately after deployment. Define post-change verification steps (service health checks, integrity scans, user acceptance) and keep the change in “observe” mode for a defined period before closing the ticket.
-
Documentation, asset updates, and lessons learned.
Record approvals, test evidence, and any incidents in the change record. Update the asset inventory or CMDB to reflect configuration changes. Hold a short post-change review for significant changes to capture lessons and improve future security impact analyses.
Example in a Small or Medium Business
A mid-sized engineering firm needs to free memory on a file server; a system administrator, Alice, proposes uninstalling the endpoint protection agent to reduce RAM usage. She creates a change request using the company template that lists the affected server, data classification, and a proposed rollback plan. The change request includes a Security Impact Analysis where Alice notes potential loss of malware protection and increased exposure to ransomware. The change is routed to the CCB, which includes the security owner and a network admin; they score the impact as High for confidentiality and integrity and reject the uninstall option. The board recommends purchasing a RAM upgrade and testing the upgrade in the staging environment first. Alice schedules the RAM increase in a maintenance window, takes a snapshot backup, and runs validation checks after installation. Post-change monitoring shows normal behavior, and the change record is updated with test evidence and a brief lessons-learned note. This process prevented an insecure shortcut and documented the decision for auditors and future reference.
Summary
Requiring a documented security impact analysis before making changes combines policy, process, and simple technical controls to prevent accidental exposure or service failure. For SMBs, practical measures—formalizing a CCB, using standardized change requests with a security section, performing staged testing with rollback plans, and enforcing post-change monitoring—create a low-overhead, repeatable workflow that satisfies the control and reduces risk to confidentiality, integrity, and availability.